Contractors

SITE CLEARING PHOTOGRAPHS
The State of Mississippi/PUL Alliance completed its work on the site clearing for the project and turned the site over to Toyota in April 2007. The following photographs show the work that has been done on the site so far.
Frontage road construction Electric plant

ENGINEERING CONTRACTS
The PUL (Pontotoc, Union & Lee) Alliance advertised and received Engineering qualifications from 18 Engineering, Environmental and Architectural firms. The advertisement requested qualifications for the design and construction administration of water, wastewater, natural gas and rail infrastructure. Of the 18 responses, one architectural response and one environmental response were received but were not qualified for the specific work as advertised. The PUL evaluated the remaining 16 proposals and recommended the award of four contracts. The four contracts are as follows: Elevated water storage tank design contract to Precision Engineering of New Albany, Elevated water storage tank design to CivilTech, Inc. (MBE) of Jackson, Natural Gas pipeline design to Tennergy, Inc. of Pontotoc and the development of design parameters for water and wastewater to Cook Coggin, Inc. of Tupelo.

There still remains to be awarded the design of the rail spur to the site and the water and wastewater line design which is anticipated to be handled in possibly two design contracts.

Future construction to be funded by the State thru the PUL Alliance will entail the same projects as described in the engineering description above. A synopsis is as follows:
COMPLETE

  • Water TankElevated Water Storage Tank contract award to CB&I Inc. To be completed by July 10, 2008.
  • The elevated tank construction bid advertisement was placed on Wednesday June 20, 2007 and bids will be taken on Tuesday June 26, 2007. Award is anticipated to be made on June 28th. Select Elevated Water Storage Tank to view the advertisement for proposals.

IN PROGRESS

Updated Information on Infrastructure (as of April, 2008)

  • Wastewater pumping stations, water transmission booster station, and other components to be completed in conjunction with water and sewer line work.
  • Project Onsite Water and Wastewater Lines: to be advertised Mid-May
  • Project # 1 awarded to ARGO Const. 15,000 L.F. of parallel 30 inch ductile iron water line and 18 inch ductile iron wastewater force main.
  • Project # 2 anticipated bid date late May 2008. 30,000 L.F. of parallel 30 inch ductile iron water main and 18 inch wastewater force main.
  • Project # 10 anticipated bid date June 2008. 7000 L.F. of parallel 30 inch ductile iron water main and 18 inch wastewater force main.
  • Project # 11 awarded to TRAX Inc. for installation of 24 inch wastewater force main and casings.
  • Project for installation of 12 inch natural gas main awarded to Freeland and Lemm Construction Inc.
  • Project for construction of natural gas metering station awarded to James N. Bush Construction Co.
  • Rail spur project anticipated to be advertised by end of May of first of June 2008. Construction of 10,000 LF of spur track and 8500 LF of mainline sidings. Includes bridges over State Hwy 178 and HWY 78 (Future I-22) and County Road bridge over rail spur.
  • “Magnolia Way”, Toyota frontage road contract awarded by MDOT to Hill Bros Const. Co. Inc. Milestone 1 area to be completed by Dec 2008, remainder completed by August 2009.
  • Blue Springs Interchange Improvements: Construction advertisement anticipated June 2008.

Select Engineering Consulting Services to see an list of companies procured by the PUL Alliance.